How Long Does an 80 kVA UPS Work? Duration Table and Calculation

How Long Does an 80 kVA UPS Work? Duration Table and Calculation

80 kVA UPS; It is used for large factories, hospitals, data centers, telecom facilities and large commercial buildings. At this power, DC current exceeds 170 amps at full load and the battery bank requires a separate battery room. With the same battery group, the operating time at full load is more than half compared to a 40 kVA UPS. In this article, we explained the time table, calculation method and the maximum amount of battery that can be connected to the UPS.

Short answer

The DC voltage of an 80 kVA UPS is usually 480 V (40 x 12 V batteries). Refer to the label and data sheet for the number of batteries. Approximate times with a 480 V group:

  • At full load (approx. 100 W) with 72000 Ah batteries: 14 minutes
  • At half load (approx. 100 W) with 36000 Ah batteries: approx. 35 minutes
  • At full load with 200 Ah batteries: approx. 35 minutes
  • At half load with 200 Ah batteries: approx. 1 hour 27 minutes

How many watts does an 80 kVA UPS carry?

  • A UPS with a power factor of 0.9 has 80 kVA approx. 72000 W does.
  • In the new generation model with a power factor of 1,0 80000 W does.
  • In the old model with a power factor of 0.8 64000 W does.

The power factor is written in the data sheet. See What is Power Factor?.

Large-capacity 12V UPS batteries stacked on a three-deck rack

Time table for 80 kVA UPS (40 x 12 V batteries, 480 V DC)

Durations for new VRLA/AGM battery, 25 °C and 0.9 power factor and 90% UPS efficiency They are rough calculations. The actual time may deviate by 20-30% ± depending on the model.

Ah on each batteryFull load (72000 W)75% load (54000 W)Half load (36000 W)25% load (18000 W)
65 Ah8 min12 min20 min49 min
100 Ah14 min21 min35 min1 hr 27 min
150 Ah24 min35 min59 min2 hr 25 min
200 Ah35 min51 min1 hr 27 min3 hr 30 min
300 Ah (2 V cell group)59 min1 hr 27 min2 hr 25 min5 hr 35 min
500 Ah (2 V cell group)1 hr 55 min2 hr 45 min4 hr 30 min9 hr 55 min

The 300 and 500 Ah rows are for a group of 240 2 V cells (480 V). In 12 V blocks, the largest practical Ah value is around 200 Ah.

Data center server hall protected by UPS

Example calculation: 48000 W load in data center

In a data center, servers, storage, network devices and cooling control equipment draw a total of 48000 W. The UPS is 480 V, there are 40 150 Ah batteries in the battery pack.

  1. Battery energy: 40 × 12 V × 150 Ah = 72000 Wh.
  2. Current: 48000 ÷ (0.9 × 40 × 11.5 V) = approximately 116 A.
  3. C-rate: 116 ÷ 150 = approximately 0.77.
  4. Available rate: Since the C-ratio is between 0.5-1, it is 0.50 (for the ratio table 1 kVA inscription see).
  5. Duration: 72000 × 0.50 ÷ 48000 = 0.75 hours, so about 45 min.

If the goal is 1 hour, repeat with 200 Ah batteries: Wh = 96000, C-ratio approx. 0.58, ratio 0.50. Duration = 96000 × 0.50 ÷ 48000 = 60 minutes.

For load analysis, see. UPS and Battery Capacity Project Design.

Engineer inspecting battery rack in battery room

What is the maximum amount of battery connected to an 80 kVA UPS?

The number of batteries is fixed

For the 480 V model, 40 12 V batteries are connected in series. You cannot change this number. To extend the time, you can switch to batteries with larger Ah or add parallel from the same string. The number of parallel strings is usually limited to 2-4. Refer to the manufacturer's data sheet. See What is a Battery String?.

Charging current is the most important limit

At this power, the charging current is usually around 20 A in standard models. In long-run models, it can be 40 A or above. The exact value is in the data sheet.

Rule: Ah = charging current × 10 (comfortable) to 20 × (limit).

UPS charging currentRecommended maximum battery (Ah)Full charge time (roughly)
20 A200-400 Ah12-24 hours
30 A300-600 Ah12-24 hours
40 A400-800 Ah12-24 hours
60 A600-1200 Ah12-24 hours

Coarse charging time: Ah × 1.2 ÷ charging current (hours). For 200 Ah in the data center example above, 10-20 A is sufficient. For a batch of 500 Ah, at least 25-50 A is recommended.

DC current, cable and protection

At full load, DC current is approximately 174 A. At this level, cable cross-section, DC fuse and switch selection should be made calculated. As the cable distance increases, loss and heating increase. The UPS and battery pack should be positioned as close as possible.

Weight, space and ventilation

40 12 V 150 Ah batteries hold approx. 1700-1900 kg, 40 12 V 200 Ah batteries approx. 2300-2500 kg. For this weight, the floor load and rack load-bearing capacity must be checked by the engineer before installation. Ventilation, temperature control and fire safety are planned separately in the battery room. Temperature matters: when the ambient temperature increases by 10 °C, the VRLA battery life is roughly halved. See Factors Affecting Battery Life.

Highest Ah battery

The practical upper limit for single block 12 V batteries is around 200 Ah. Larger capacities use 2 V cells (OPzV/OPzS). See What is OPzS and OPzV Battery?. If space and weight are a problem, a lithium battery is also an option. See Lithium-Ion UPS Batteries and What is Thermal Runaway? How to Prevent It in Batteries?.

Security: 480 V DC is life-threatening. Battery addition, connection and insurance are the work of authorized personnel.

Single UPS or parallel at 80 kVA?

Running two 40 kVA UPSs in parallel at this power (three for N+1) provides redundancy and maintains the load during maintenance. See What is Redundancy in UPS?, Parallel UPS Installation and Load Sharing and UPS Architecture in Data Centers. If there is an expectation of growth Modular UPS is also an option.

Summary for all kVA classes on one page: How Long Does a UPS Work? kVA Guide

Frequently Asked Questions

01Does an 80 kVA UPS run for 1 hour?
At a load of up to 36000 W, you get about 1 hour with 150 Ah batteries, and about 1 hour and 27 minutes with 200 Ah batteries. For 1 hour at full load, you need a group of about 300 Ah with 2 V cells.
02Is a battery room required for an 80 kVA UPS?
Yes, it is a must in practice. It requires 40 large batteries, racks, ventilation and fire safety.
03Do I need a generator?
If the goal is to run longer than 30-60 minutes at full load, the generator is often more economical. See Differences Between UPS and Generator.
04How do I verify duration?
The most reliable method is the discharge test. See Discharge and Load Tests.

Let's Choose the Right UPS Together

Bempower https://www.bemenerji.com/en/blog/how-long-does-an-80-kva-ups-work-duration-table-and-calculation