How Long Does a 60 kVA UPS Work? Duration Table and Calculation

How Long Does a 60 kVA UPS Work? Duration Table and Calculation

60 kVA UPS; It is used for large factories, hospital blocks, hotel and shopping mall technical rooms, data rooms and telecom facilities. At this power, the battery bank no longer fits in a cabinet and often a separate battery room is required. The duration depends on the battery capacity as well as the area of the battery room, floor load and ventilation. In this article, we explained the time table, calculation method and the maximum amount of battery that can be connected to the UPS.

Short answer

The DC voltage of a 60 kVA UPS is usually 480 V (40 x 12 V batteries). Some models use different voltages (e.g. ±240 V). Refer to the label and data sheet for the number of batteries. Approximate times with a 480 V group:

  • At full load (approx. 54000 W) with 100 Ah batteries: 20 minutes
  • At half load (approx. 27000 W) with 100 Ah batteries: approx. 50 minutes
  • At full load with 200 Ah batteries: approx. 50 minutes
  • At half load with 200 Ah batteries: approx. 2 hours and 5 minutes

How many watts does a 60 kVA UPS carry?

  • In a UPS with a power factor of 0.9, 60 kVA is approximately 54000 W does.
  • In the new generation model with a power factor of 1,0 60000 W does.
  • In the old model with a power factor of 0.8 48000 W does.

The power factor is written in the data sheet. See What is Power Factor?.

Battery room with battery groups arranged on racks

Time table for 60 kVA UPS (40 x 12 V batteries, 480 V DC)

Durations for new VRLA/AGM battery, 25 °C and 0.9 power factor and 90% UPS efficiency They are rough calculations. The actual time may deviate by 20-30% ± depending on the model.

Ah on each batteryFull load (54000 W)75% load (40500 W)Half load (27000 W)25% load (13500 W)
65 Ah12 min17 min29 min1 hr 12 min
100 Ah21 min30 min51 min2 hr 5 min
150 Ah35 min51 min1 hr 27 min3 hr 30 min
200 Ah51 min1 hr 14 min2 hr 5 min4 hr 50 min
300 Ah (2 V cell group)1 hr 27 min2 hr 5 min3 hr 30 min7 hr 45 min

The 300 Ah row is for a group of 240 2 V cells (480 V). In 12 V blocks, the largest practical Ah value is around 200 Ah.

Server rack rows in data room protected by UPS

Example calculation: 36000 W load in data room

In a data room, servers, storage, network devices and precise cooling control draw a total of 36000 W. The UPS is 480 V, there are 40 100 Ah batteries in the battery pack.

  1. Battery energy: 40 × 12 V × 100 Ah = 48000 Wh.
  2. Current: 36000 ÷ (0.9 × 40 × 11.5 V) = approximately 87 A.
  3. C-rate: 87 ÷ 100 = approximately 0.87.
  4. Available rate: Since the C-ratio is between 0.5-1, it is 0.50 (for the ratio table 1 kVA inscription see).
  5. Duration: 48000 × 0.50 ÷ 36000 = 0.67 hours, so about 40 minutes.

If the goal is 1 hour, repeat the calculation with 150 Ah batteries: Wh = 72000, C-rate approx. 0.58, ratio 0.50. Duration = 72000 × 0.50 ÷ 36000 = 60 minutes. So 150 Ah is required per battery.

For load analysis, see. UPS and Battery Capacity Project Design.

Technician in insulating gloves checking battery pack switch box

What is the maximum amount of battery connected to a 60 kVA UPS?

The number of batteries is fixed

For the 480 V model, 40 12 V batteries are connected in series. You cannot change this number. To extend the time, you can switch to batteries with larger Ah or add parallel from the same string. The number of parallel strings is usually limited to 2-4. Refer to the manufacturer's data sheet. See What is a Battery String?.

Charging current is the most important limit

At this power, the charging current is usually around 10-20 A in standard models. In long-run models, it can be 40 A or above. The exact value is in the data sheet.

Rule: Ah = charging current × 10 (comfortable) to 20 × (limit).

UPS charging currentRecommended maximum battery (Ah)Full charge time (roughly)
10 A100-200 Ah12-24 hours
20 A200-400 Ah12-24 hours
30 A300-600 Ah12-24 hours
40 A400-800 Ah12-24 hours

Coarse charging time: Ah × 1.2 ÷ charging current (hours). For 150 Ah in the data room example above, 8-15 A is sufficient.

DC current, cable and protection

At full load, DC current is approximately 130 A. At this level, cable cross-section, DC fuse and switch selection should be made calculated. The loss increases as the cable distance increases. The UPS and battery pack should be positioned as close as possible.

Weight, space and ventilation

40 12 V 150 Ah batteries hold approximately 1700-1900 kg, 40 12 V 200 Ah batteries approximately 2300-2500 kg. For this weight, the floor load and rack carrying capacity must be checked by the engineer before installation. Ventilation, temperature control and fire safety are planned separately in battery rooms. See Lithium Battery Cabinet Installation: Layout, Ventilation, and Safety Distances (written for lithium, the principles of settlement are similar).

Highest Ah battery

The practical upper limit for single block 12 V batteries is around 200 Ah. Larger capacities use 2 V cells (OPzV/OPzS). See What is OPzS and OPzV Battery?. If space and weight are a problem, a lithium battery is also an option. See Lithium-Ion UPS Batteries and What is Thermal Runaway? How to Prevent It in Batteries?.

Security: 480 V DC is life-threatening. Battery addition, connection and insurance are the work of authorized personnel.

Single UPS or parallel at 60 kVA?

If an interruption in this power is not acceptable, two UPSs are operated in parallel (N+1 or 2N). If one fails or is serviced, the other bears the load. See What is Redundancy in UPS? and UPS Architecture in Data Centers. If the burden will grow over time Modular UPS See the solution.

Frequently Asked Questions

01Does a 60 kVA UPS run for 1 hour?
At a load of up to 27000 W, you get about 50 minutes with 100 Ah batteries, and about 1 hour and 27 minutes with 150 Ah batteries. For 1 hour at full load, about 250 Ah per battery is required, and in this case, a group with 2 V cells is installed.
02Is a battery room required for a 60 kVA UPS?
For 40 large batteries, most of the time yes. Especially groups of 150 Ah and above do not fit in the battery cabinet.
03Do I need a generator?
If there is a target of running longer than 1 hour at full load, the generator is often more economical. See Differences Between UPS and Generator.
04How do I verify duration?
The most reliable method is the discharge test. See Discharge and Load Tests.