How Long Does a 400 kVA UPS Work? Duration Table and Calculation

How Long Does a 400 kVA UPS Work? Duration Table and Calculation

A 400 kVA level no longer means a single UPS, but a system where multiple units work in parallel. Large data center halls, hospital campuses, and organized industrial facilities are installed on this scale. At full load, the total DC current reaches over 850 amps. In this article, we explained the time table, calculation method, and the maximum amount of battery that can be connected to the system.

Short answer

The battery bank of a 400 kVA UPS system is usually 480 V DC (40 12 V blocks or 240 2 V cells). Some manufacturers use different voltages, such as 576 V. A single battery string is not enough at this power. More than one string is connected in parallel and the time is total Ah value determined accordingly. In this article, all times are given over the total Ah. Approximate times:

  • At full load (approx. 360000 W) with a total of 1500 Ah: approx. 59 minutes
  • At full load with a total of 2000 Ah: approx. 1 hour and 27 minutes
  • At half load (approx. 180000 W) with a total of 2000 Ah: approx. 3 hours 30 minutes
  • At full load with a total of 4000 Ah: approx. 3 hours 30 minutes

The calculations were made with 90% efficiency and 0.9 power factor. Since the efficiency of the new generation large UPSs is higher, the actual times may be a little longer. In most projects, the target time is 10-30 minutes. This time acts as a bridge until the generator is activated.

How many watts does a 400 kVA UPS carry?

  • In the system with a power factor of 0.9, 400 kVA is approximately 360000 W does.
  • In the new generation model with a power factor of 1,0 400000 W does.
  • In the old model with a power factor of 0.8 320000 W does.

The power factor is written in the data sheet. See What is Power Factor?.

Three parallel battery strings, each with its own DC switch

Time table for 400 kVA UPS (480 V DC, total Ah)

Durations for new VRLA/AGM battery (2 V cell), 25 °C and 0.9 power factor and 90% UPS efficiency They are rough calculations. The actual time may deviate by 20-30% ± depending on the model. "Total Ah" is the sum of the Ah values of all 480 V arrays connected in parallel.

Total battery capacityFull load (360000 W)75% load (270000 W)Half load (180000 W)25% load (90000 W)
1000 Ah35 min51 min1 hr 27 min3 hr 30 min
1500 Ah59 min1 hr 27 min2 hr 25 min5 hr 35 min
2000 Ah1 hr 27 min2 hr 5 min3 hr 30 min7 hr 45 min
3000 Ah2 hr 25 min3 hr 30 min5 hr 35 minOver 12 h
4000 Ah3 hr 30 min4 hr 50 min7 hr 45 minOver 12 h

The calculation loses its reliability for periods above 12 hours. A generator solution is used for such a long time at this power.

Data center server hall protected by UPS

Example calculation: 260000 W load in data center hall

In a data center hall, server rack rows, storage systems, network core and precise cooling control draw a total of 260000 W. The UPS system has 480 V DC input, total battery capacity 2000 Ah.

  1. Battery energy: 480 V × 2000 Ah = 960000 Wh.
  2. Current: 260000 ÷ (0.9 × 40 × 11.5 V) = approximately 628 A (sum of all sequences).
  3. C-rate: 628 ÷ 2000 = approximately 0.31.
  4. Available rate: Since the C-ratio is between 0.2-0.5, 0.60 (for the ratio table 1 kVA inscription see).
  5. Duration: 960000 × 0.60 ÷ 260000 = 2.22 hours, so about 133 minutes.

If the target is 3 hours, repeat with the group of a total of 3000 Ah: Wh = 1440000, C-ratio approx. 0.21, ratio 0.60. Duration = 1440000 × 0.60 ÷ 260000 = approx 199 minutes.

For load analysis, see. UPS and Battery Capacity Project Design.

Engineer checking DC switch board in battery hall

What is the maximum amount of battery connected to a 400 kVA UPS?

The number of batteries is fixed, the number of parallel strings is limited

Each string connects 240 2 V cells (480 V) in series. You cannot change this number. To extend the time, the cell Ah value is increased or a parallel array is added. At this power, each UPS unit usually has its own battery string, and the sum of these strings makes up the total Ah value of the system. The highest number of parallel strings in the manufacturer's data sheet and the total Ah limit must be observed. See What is a Battery String?.

Charging current is the most important limit

At this power, the charging current is not provided by a single circuit. The charging circuit of each UPS unit is collected or a separate charging rectifier is added. The exact value is in the data sheet.

Rule: Ah = charging current × 10 (comfortable) to 20 × (limit).

Total charging currentRecommended maximum total battery (Ah)Full charge time (roughly)
100 A1000-2000 Ah12-24 hours
200 A2000-4000 Ah12-24 hours
400 A4000-8000 Ah12-24 hours
800 A8000-16000 Ah12-24 hours

Rough charging time: Ah × 1.2 ÷ charging current (hours). In the example above, a total charging current of 100-200 A is required for 2000 Ah, and 150-300 A for 3000 Ah.

DC current, busbar and protection

At full load, the total DC current is about 870 A. This current does not flow through a single string. Each string must have its own DC fuse and switch. Copper busbar cross-sections, short-circuit strength, and busbar distances require project engineering.

Weight, space and ventilation

A group of 2 V cells of 480 V weighs roughly 15 kg × Ah. For example, 2000 Ah costs about 30 tons, 4000 Ah about 60 tons. For these weights, the floor load and rack-bearing capacity must be verified by static calculation before installation. Ventilation, temperature, and fire safety in the battery room are planned separately. See Factors Affecting Battery Life.

Lithium option

If space and weight are a problem, a lithium battery is also an option. See Lithium-Ion UPS Batteries and What is Thermal Runaway? How to Prevent It in Batteries?. For 2 V cells, see V. What is OPzS and OPzV Battery?.

Security: 480 V DC is life-threatening. Battery addition, connection and insurance are the work of authorized personnel.

Is 400 kVA a single UPS or a system?

Typical solutions for 400 kVA are two 200 kVA, four 100 kVA or modular construction. Each unit can have its own battery array. When N+1 is installed with three units, two units can carry the load even if one fails. The number of units and their parallel limits vary by manufacturer. See What is a Modular UPS?, What is Redundancy in UPS?, Parallel UPS Installation and Load Sharing and UPS Architecture in Data Centers.

Summary for all kVA classes on one page: How Long Does a UPS Work? kVA Guide

Frequently Asked Questions

01Will a 400 kVA UPS run for 1 hour?
With a total group of 2000 Ah at a load of up to 180000 W, you get about 3 hours and 30 minutes, and with a group of 1500 Ah, you get about 2 hours and 25 minutes. For 1 hour at full load, a group of about 1500 Ah is required.
02Is a battery room required for a 400 kVA UPS?
Yes, as well as a large battery room. The rack requires ventilation, temperature control, fire safety, and floor bearing capacity.
03Do I need a generator?
If the goal is to run longer than 30 minutes at full load, the generator is almost always more economical. See Differences Between UPS and Generator.
04How do I verify duration?
The most reliable method is the discharge test. See Discharge and Load Tests.