How Long Does a 120 kVA UPS Work? Duration Table and Calculation

How Long Does a 120 kVA UPS Work? Duration Table and Calculation

120 kVA UPS; It is used for large data center halls, hospital blocks, manufacturing facilities and telecom centers. At this power, DC current exceeds 250 amps at full load. With the same battery group, the time is shortened by about a fifth compared to a 100 kVA UPS. In this article, we explained the time table, calculation method and the maximum amount of battery that can be connected to the UPS.

Short answer

The DC voltage of a 120 kVA UPS is usually 480 V (40 x 12 V blocks or 240 x 2 V cells). Some models use different voltages, such as 360 V, ±240 V or 576 V. Refer to the label and data sheet for the number of batteries. Approximate times with a 480 V group:

  • At full load (approx. 108000 W) with 200 Ah (12 V block): 20 minutes
  • At full load with 500 Ah (2 V cell): approx. 1 hour 10 minutes
  • At half load with 500 Ah (approx. 54000 W): approx. 2 hours and 45 minutes
  • At full load with 1000 Ah: approx. 2 hours 45 minutes

For most projects, the target time is 10-30 minutes. This time acts as a bridge until the generator kicks in.

How many watts does a 120 kVA UPS carry?

  • 120 kVA in a UPS with a power factor of 0.9 is approximately 108000 W does.
  • In the new generation model with a power factor of 1,0 120000 W does.
  • In the old model with a power factor of 0.8 96000 W does.

The power factor is written in the data sheet. See What is Power Factor?.

2 V battery cells connected in series in two-story racks

Time table for 120 kVA UPS (480 V DC)

Durations for new VRLA/AGM battery, 25 °C and 0.9 power factor and 90% UPS efficiency They are rough calculations. The actual time may deviate by 20-30% ± depending on the model. If there is a 200 Ah line, 40 pcs are for 12 V blocks, the others are for 240 pcs 2 V cells.

Ah value of the battery packFull load (108000 W)75% load (81000 W)Half load (54000 W)25% load (27000 W)
200 Ah (12 V block)21 min30 min51 min2 hr 5 min
300 Ah (2 V cell)35 min51 min1 hr 27 min3 hr 30 min
500 Ah (2 V cell)1 hr 8 min1 hr 39 min2 hr 45 min6 hr 15 min
800 Ah (2 V cell)2 hr 5 min3 h4 hr 50 min10 hr 40 min
1000 Ah (2 V cell)2 hr 45 min3 hr 55 min6 hr 15 minOver 12 h

The calculation loses its reliability for periods above 12 hours. A generator solution is used for such a long time at this power.

Hospital intensive care and operating room corridor protected by UPS

Example calculation: 80000 W load in hospital

In a hospital, the operating room, intensive care, imaging devices and server room draw a total of 80000 W. UPS 480 V DC input, battery group 500 Ah (240 x 2 V cells).

  1. Battery energy: 480 V × 500 Ah = 240000 Wh (240 cells × 2 V × 500 Ah).
  2. Current: 80000 ÷ (0.9 × 40 × 11.5 V) = approximately 193 A.
  3. C-rate: 193 ÷ 500 = approximately 0.39.
  4. Available rate: Since the C-ratio is between 0.2-0.5, 0.60 (for the ratio table 1 kVA inscription see).
  5. Duration: 240000 × 0.60 ÷ 80000 = 1.8 hours, so about 108 minutes.

If the target is 3 hours, repeat with the group of 800 Ah: Wh = 384000, C-ratio approx. 0.24, ratio 0.60. Duration = 384000 × 0.60 ÷ 80000 = approx 173 minutes.

For load analysis, see. UPS and Battery Capacity Project Design.

Technician checks bus connection between battery cells with insulating torque wrench

What is the maximum amount of battery connected to a 120 kVA UPS?

The number of batteries is fixed

In the 480 V model, 40 12 V blocks or 240 2 V cells are connected in series. You cannot change this number. To extend the time, switch to cells with larger Ah or add parallel from the same array. The number of parallel strings is usually limited to 2-4. Refer to the manufacturer's data sheet. Since the DC current of a single battery string of this power is very high, most projects use two or more parallel strings. See What is a Battery String?.

Charging current is the most important limit

At this power, the charging current can be 20-60 A or above depending on the model. The exact value is in the datasheet.

Rule: Ah = charging current × 10 (comfortable) to 20 × (limit).

UPS charging currentRecommended maximum battery (Ah)Full charge time (roughly)
20 A200-400 Ah12-24 hours
40 A400-800 Ah12-24 hours
60 A600-1200 Ah12-24 hours
100 A1000-2000 Ah12-24 hours

Rough charging time: Ah × 1.2 ÷ charging current (hours). In the hospital example above, a charging current of 25-50 A is required for 500 Ah, and 40-80 A for 800 Ah.

DC current, cable and protection

At full load, DC current is approximately 261 A. At this level, the selection of copper bus or large cross-section cable, DC fuse and switch must be made with calculation. Positioning the battery pack as close as possible with the UPS reduces both loss and heating.

Weight, space and ventilation

40 12 V 200 Ah blocks hold approximately 2300-2500 kg. 240 units of 2 V 300 Ah cells hold approximately 4500-5000 kg, 500 Ah cells approximately 7000-8000 kg, 800 Ah cells approximately 11500-12500 kg. For these weights, the floor load and rack carrying capacity must be verified by static calculation before installation. Ventilation, temperature and fire safety in the battery room are planned separately. See Factors Affecting Battery Life.

Highest Ah battery

The practical upper limit of 12 V blocks is around 200 Ah. For 300 Ah and above, 2 V cells (OPzV/OPzS) are used at this power. See What is OPzS and OPzV Battery?. If space and weight are a problem, a lithium battery is also an option. See Lithium-Ion UPS Batteries and What is Thermal Runaway? How to Prevent It in Batteries?.

Security: 480 V DC is life-threatening. Battery addition, connection and insurance are the work of authorized personnel.

Single UPS at 120 kVA, modular or parallel?

In facilities that are not tolerant of interruptions, such as hospitals and data centers, N+1 or 2N redundancy is preferred instead of a single UPS. If one fails or is taken into maintenance, the other carries the load. If the load will grow over time, gradual investment can be made with a modular UPS. See. What is a Modular UPS?, What is Redundancy in UPS?, Parallel UPS Installation and Load Sharing and UPS Architecture in Data Centers.

Summary for all kVA classes on one page: How Long Does a UPS Work? kVA Guide

Frequently Asked Questions

01Does a 120 kVA UPS run for 1 hour?
At a load of up to 54000 W, you get about 2 hours and 45 minutes with a group of 2 V cells of 500 Ah, and about 1 hour and 27 minutes with a group of 300 Ah. For 1 hour at full load, a group of about 450 Ah is required.
02Is a battery room required for a 120 kVA UPS?
Yes, it is essential in practice. Racking requires ventilation, temperature control, and fire safety.
03Do I need a generator?
If the goal is to run longer than 30 minutes at full load, the generator is almost always more economical. See Differences Between UPS and Generator.
04How do I verify duration?
The most reliable method is the discharge test. See Discharge and Load Tests.