What is a Static Transfer Switch (STS)? Usage in Dual Source Supply
Whether in a server room, an operating room, or a production line, a power outage starts with the failure of a single line. That's why critical facilities often have two independent supplies. But even if there are two lines, how the load will pass between these two lines without feeling the interruption is a separate engineering question. This is where the Static Transfer Switch (STS) comes into play: it looks at which of the two sources is healthy and connects the load to the correct source in a fraction of a second.
In this article, we discuss step by step what STS is, which components it works with, its difference with mechanical transfer switch (ATS), its place in dual-source (A/B) feed architectures and its sizing criteria. Article; It was prepared for IT and facility managers, business owners, technical service and purchasing units. The selection and maintenance sections are for those who are looking for an answer to the question "Is STS really necessary in our facility?".
Safety note: The devices described here operate with high current and voltage. Installation, connection, adjustment and fault intervention should be carried out by authorized electrical personnel or technical service. The article is for informational purposes only, not an application instruction.
What is a static transfer switch (STS)?
STS is an electronic switch that is fed from two independent AC sources and outputs to a single critical load. Normally, it feeds the load from the preferred (primary) source; if the voltage of this source goes beyond the accepted range, it transfers the load to the alternative source. It is called "static" because it does this not with mechanical contacts, but with thyristors (SCR) or similar semiconductor switches. In other words, there are no moving parts, arcs and contact wear; the speed of the transition is determined by the response time of the semiconductor and the control algorithm.
This definition also coincides with the scope of the IEC 62310 series. The standard series deals with stand-alone static transfer systems and systems up to 1 000 V, aiming to ensure the continuity of the load from two or more independent AC sources in a controlled transfer. The series consists of three parts: general and safety requirements, electromagnetic compatibility (EMC) requirements, and the method of determining performance and test requirements.
An important distinction: STS is not an energy source. It does not contain batteries, does not store energy, does not generate voltage. Unlike UPS, it only decides "which source will feed the load". If you want to remember the working principle of UPS How UPS works describes the trio of rectifier, battery and inverter.

How does STS work? Detection, verification, and migration
The working of an STS can be summarized in four steps:
- Continuous monitoring: The control board continuously measures the voltage waveform, amplitude, and often the frequency and phase relationship of the two sources.
- Anomaly detection: If the preferred source experiences an outage, deep collapse (sag), swell, or unacceptable degradation, a migration decision is made. Threshold values are often user-programmable.
- Verification of alternative source: The destination resource is also checked to see if it's acceptable. If both resources are broken, the migration is meaningless.
- Transition: The thyristors of the existing source are deactivated to interrupt the current, and the thyristors of the alternating source are put into conduction.
There is an important physical detail here: the thyristor is not a self-closing element; it waits for the current flowing through it to approach zero. Therefore, there is a short sequence between interrupting source A and engaging source B. To shorten this sequence, some designs use auxiliary circuits that quickly extinguish thyristors; a solution described in manufacturer applications states that the extinction time of the thyristor can go from up to 8 ms to less than 1 ms. This is a design detail that varies by architecture; what matters to you is how the total transit time is defined in the device's datasheet.
How to read the transit time?
In industry sources, typical transit times for STS are between about 2 ms and 8 ms, and in some applications up to 12 ms, including sensing time. For example, a medium voltage STS paper states that the total sensing and transient time for voltage loss can range from around 2.5 ms to closer to 12 ms for voltage spikes. This range is not an "exact number"; the sensing threshold, load type, transformer, and type of voltage breakdown change the result. When comparing Is detection time included? Be sure to ask the question.
Why are milliseconds important? ITIC curve and energy retention time
Switching power supplies (SMPS) of computers, servers, and network devices have a short energy retention time in their internal capacitors. During this time, the device continues to operate even if the mains is interrupted. This behavior is described by the ITIC (CBEMA) curve for information technology equipment. The curve shows the magnitude and duration of voltage degradation in an envelope; the equipment is expected to continue to function in events that remain within the envelope.
- Tension tolerance of about ±10% in continuous state,
- Tolerance up to approx. 20 ms at full interruptions when the voltage drops to zero (one cycle at 50 Hz),
- Tolerance up to approximately 0.5 seconds on crashes where voltage drops to 70% of nominal.
The ITIC curve is actually prepared for 120 V / 60 Hz systems; however, since the equipment responds to physical time, the percentage voltage limits and millisecond values are used as a guide in 230 V / 50 Hz systems. Note that the curve is a general recommendation, each device should be consulted with its own manufacturer data. The Socomec technical note on STS emphasizes that the typical transfer time is at the level of 4-6 ms, i.e. below one cycle, and that this remains within the limits of the ITIC curve.
Definition of events that disrupt voltage quality in the electricity network (interruption, collapse, rise) What is power quality You can find it in the article. In this article, let's just note this: STS manages grid degradation by transferring the load to the healthy source, not by "waiting for it to pass".
What is the difference between STS and ATS?
Both devices "switch between two sources"; the difference is how they do it and how long it takes. ATS (Automatic Transfer Switch) works with a mechanical contactor or switch; STS uses semiconductors. In data center sources, values extending up to tens of ms are given for the response time of the mechanical switch; there are also sources that give longer values (20-100 ms band) for ATS. Since the difference varies by product and load condition, the values in the table only show the general order.
| Feature | STS (static) | ATS (mechanical) |
|---|---|---|
| Switching element | Thyristor (SCR) or similar semiconductor | Contactor, relay or motorised switch |
| Typical transit time | A few ms (quarter-half cycle order) | Tens of ms and above |
| Arc and contact wear | None; no moving parts | Yes; contacts wear out over time |
| Loss in normal operation | Higher due to semiconductor conduction loss; may require heating and fan | Very low loss with contacts closed |
| Typical use | Critical loads such as server room, sensitive process, medical imaging | Short interruption resistant loads such as mains-generator transition, lighting, pumps, air conditioning |
| Major risk | Semiconductor failure can block the transition; possibility of being a single point of failure | Failure to feed the load during the transit period |
As a rule of thumb: if the load cannot tolerate a few tens of milliseconds of interruption, consider STS; if a recommissioning of seconds on the transition from the grid to the generator is already accepted, ATS is sufficient. The interoperability of the generator and UPS is a separate matter; Differences between a UPS and a generator The text tells which device undertakes which task.

Where is STS used in double source feed?
"Dual source" doesn't mean the same thing everywhere. STS can be placed at different points in the plant's energy architecture.
1. Switching between two mains lines
In some industrial sites, office parks or critical facilities, two separate supply lines can be purchased from the distribution company. STS carries the load to the healthy one between these two lines. In such a design, it is important that the lines are truly independent; two lines connected to the same transformer or the same cable duct give the appearance of redundancy but carry the risk of common failure.
2. Between UPS outlets (A/B supply)
This is the most common use in data center and server rooms: there are two separate UPS lines (A and B) and their outputs are combined with STS to a single distribution point, for example a to the power distribution unit (PDU) is given. Thus, when one UPS line is maintained or fails, the load passes to the other line without interruption. Redundancy concepts (N+1, 2N, parallel UPS) Redundancy in UPS In his article, he explained the layer approach in data centers UPS architecture in data centers You can find it in the article.
3. Between the mains and the generator
In manufacturer applications, we also see STS described in layouts where one source is the grid and the other is the generator. However, in this use, the voltage and frequency of the generator must be stable. The generator output is generally more volatile in phase and frequency than the grid; therefore, in most facilities, generator switching is done with ATS, and protection of sensitive loads is done with UPS. Generator and UPS interaction Frequency and synchronization problems in generator-fed UPS You can continue from the article.
4. Rack-level (for single-cable devices)
By using a small "rack STS" or "rack ATS" in the rack, devices with only one power cable can be redundancy from two lines. We cover this separately in the next section.

Rack transfer switch for single-plug devices
Most server and network devices come with two power supplies; each connects to a separate line (A and B), and if one line goes, the other takes over the load. However, equipment with a single power cable such as a storage unit, firewall, legacy server, audio or broadcast device cannot benefit from this advantage. In this case, even if there is a dual line infrastructure, the device connected to a single line shuts down when that line goes.
Schneider Electric's white paper for single-cable equipment in a dual-line environment breaks down three basic approaches: leaving it connected mostly with a single line, using an in-rack transfer switch, and resolving at the distribution level with a larger-scale STS. A rack transfer switch is a device, usually 1U or 2U, with two input cables and device receptacles on it; the single-cable device plugs directly into these receptacles. Products may be referred to as "rack STS" or "rack ATS"; therefore, it is necessary to confirm the actual transit-through time from the datasheet.
Here are the points to look for when choosing:
- A dual-cable device is always the better solution; save the rack transfer switch for exceptions.
- The two inputs must come from truly independent lines (A and B); two wires plugged into the same line do not provide redundancy.
- Don't concentrate all critical devices on a single switch, as the transfer switch itself is the only point of failure.
- Remote monitoring (SNMP, web interface) and the ability to select which line is primary make it easy to route the load during maintenance.
Monitor the overall server room power layout UPS selection and maintenance for server room The article deals with it; STS should be considered as a part of this order.

Technical details to know about STS design
Synchronization and phase difference
The frequency and phase angle of the two sources should be close to each other in order not to feel the interruption. Two UPS lines fed from the same source or two outputs locked to the grid (synchronous) are suitable in this respect. If the two sources are not locked to each other, the STS may leave the load unsupplied for a short time or delay the transition in a transition with a large phase difference. According to the general approach of the standard, transfer classes (uninterrupted or short intermittent) are defined and the buyer is expected to specify this class in the specification.
Downstream transformer and inrush current
If a transformer is connected to the STS output (such as a PDU transformer in data centers), the transition between sources affects the transformer's magnetic flux. Switching at an inopportune moment can lead to large inrush current and voltage drop in the transformer. Therefore, advanced STSs use algorithms that take into account not only voltage but also transformer flux; the aim is to limit the inrush current and not extend the transition time too much. In the patent literature, it is seen why this issue is still an active engineering topic: waiting for the flux match perfectly prolongs the transition, leaving it too loose can saturate the transformer. For this reason, it is appropriate to ask the manufacturer "Which switching strategy do you use against transformer inrush current?" in systems with a transformer at the output. For inrush current behavior of motors, air conditioners and similar loads inrush current in motors, air conditioners and laser printers You can look at the article.
Backfeed protection
In any system where two sources come together, a fault of source A or a closed source must not energize the other side and the main line via the STS. The scope of IEC 62310-3 includes additional requirements for reverse feed protection testing and neutral switching as separate headings. In practice, this is critical for the safety of personnel performing line maintenance.
Neutral management
In three-phase systems, whether the neutral conductor should be switched (three-pole or four-pole STS) should be considered together with the grounding system. Incorrect selection can cause circulating currents and grounding problems. For general information about grounding behavior UPS grounding Check out the article.
How to size STS and how to choose it?
The current rating of the STS is chosen so that it can carry the entire load from either source alone. The example below only shows the method; for a real project, short-circuit resistance, ambient temperature, and manufacturer ratings should be evaluated separately.
Example calculation: STS current for three-phase 40 kVA load
Assumptions: Load 40 kVA, line voltage 400 V (three phase), 25% allowance is left for load growth and temporary increases.
- Rated current: I = S / (√3 × V) = 40 000 / (1.73 × 400) ≈ 58 A
- 25% share current: 58 × 1.25 ≈ 72 A
- The first standard grade above this value is rounded up; for example, an STS of class 80 A or 100 A is evaluated.
Both sources (for example, two UPS outlets) must be able to handle 40 kVA on their own. Otherwise, what appears to be smooth when the load is shared halfway between the two lines will exceed the capacity of the other when one line is gone. This is one of the most common scenarios for a UPS overload alarm.
Example calculation: For rack type transfer switch
Assumptions: 6 devices with one cable, 350 W each; load power factor approx. 0.95; mains 230 V.
- Total power: 6 × 350 = 2 100 W
- Apparent power: 2 100 / 0.95 ≈ 2 210 VA
- Current: 2 210/230 ≈ 9.6 A
- If the limit of about 80% is taken for continuous load: 9.6 / 0.8 ≈ 12 A; i.e. a unit of at least 16 A is suitable.
Power factor and VA-W relationship What is the power factor You can find it in detail in the article.
Selection criteria table
| By | What to look for? | Why is it important? |
|---|---|---|
| Rated current and voltage | Single-phase / three-phase, 230 V or 400 V, current rating | Each of the resources must bear the entire load |
| Transit time | Total time including detection; for which distortion types | The load must remain below the energy retention time |
| Sync window | Accepted frequency and phase difference | To ensure secure migration to independent sources |
| Transformer compatibility | Transition strategy that limits inrush current if there is an output transformer | To prevent transformer saturation and voltage drop at the time of transition |
| Reverse feed protection | Weld isolation, protection tests | Personnel and equipment safety |
| Maintenance bypass | Bypass path that supplies load when STS is disabled | In the event of STS maintenance or failure, the load must remain uninterrupted |
| Monitoring and alarm | Dry contact, SNMP, welding status indicator | To see which source you're ingested from and event logs |
| Standard compliance | IEC 62310 series and related safety/EMC documents | Provides measurable acceptance criteria in the specification |
On standards and documents UPS standards and certifications article provides the general framework. How the STS is related to the UPS's own bypass structure What is UPS bypass The article tells.
Would STS be the only point of failure? Weak points
At each point where you meet two sources in the load, that point becomes a common dependency. A failure in the semiconductor power stage of the STS can prevent the transfer of load from the main source to the alternative source under certain conditions. Therefore, it is explicitly accepted that the STS can be the single point of failure, especially in mission-critical environments, and this risk is prevented in designs.
Typical measures to reduce risk:
- Maintenance bypass: A manual way that can connect the load directly to a source when the STS fails or is undergoing maintenance.
- Load division: Distributing load groups to different STSs instead of connecting the entire load to a single STS; limits the failure effect.
- Dual-cable device preference: Leaving redundancy to the device's own power sources without ever deploying the STS on devices where possible.
- Monitoring and alarm: The fact that a resource has gone silently (i.e., the STS is running on the backup resource) is only noticeable through monitoring. About this UPS remote monitoring and alarm management The article is useful.
- Yield loss awareness: Semiconductor conduction losses lead to heating; ventilation and fan condition should be monitored in maintenance.
It is appropriate to take into account the cost of interruption when making the decision on redundancy; for this purpose The cost of a power outage to the business The approach in the article can be used.
STS maintenance and commissioning checks
STS is not a maintenance-free device. Although it does not have a moving contact, fans, condensers, heatsinks, control cards and connection points are affected over time. The following headings are usually covered in maintenance; For detailed and model-dependent steps, the manufacturer's document and authorized service should be taken as basis:
- Trace of loosening and heating at the connection points; Control with thermal camera shows hot spots early.
- Condition of the fan and ventilation paths, filter and dust accumulation.
- Voltage detection calibration and compliance of transition thresholds with the specification.
- Controlled passage test: Load conditions and possible effects should be planned in advance and carried out by authorized personnel.
- Examination of alarm and event logs; repetitive transitions are often a sign of a problem on the source side.
In STS and the critical power chain, it is necessary to plan resource migration tests with load risk and outage window in mind. On test scheduling Battery pack test scheduling and downtime risk can also be a guide for STS transition tests. For the security aspect Occupational safety in UPS and battery work We recommend you to read the article.

During initial commissioning, it is important to verify the voltage and phase sequence of the sources, record the transients and demonstrate that the alarm contacts are reaching the monitoring system correctly. For the general UPS acceptance test checklist UPS initial commissioning and acceptance tests See the article.

Common mistakes and the right approach
| Error | Conclusion | The right approach |
|---|---|---|
| The two lines are not actually independent | Nullifies the common image of point of failure redundancy | Inspect the welding, cable route, and panel chain of the lines |
| Loading both lines above 50% | When one line goes, the other is overloaded | Calculate and verify that each line can carry the entire load on its own |
| STS without maintenance bypass | STS maintenance enforces downtime | Replan the bypass path in the design |
| Comparing transit time without detection time | Misleading comparison between products | Ask about the total time and type of degradation; see the datasheet |
| Ignoring transformer output | Inrush current and voltage drop at the transition | Clarify the changeover strategy against transformer inrush current with the manufacturer |
| Putting STS on every device | Unnecessary cost and additional point of failure | Use dual-cable devices with their own redundancy; Exception the STS |
| Not monitoring | Even though the primary source is gone, it goes unnoticed | Track resource status with alarm and recording |
Is STS really necessary? Short guide to the decision
The following questions help you to simply assess the need for STS:
- Do you really have two independent sources? Otherwise, solving resource diversity first comes before STS.
- Can the load handle a few tens of milliseconds of downtime? If it can handle it, ATS is usually sufficient.
- Are the devices dual power sourced? If yes, it can be solved with A/B feeding without the need for STS.
- Are there critical devices with a single cable? Rack-level transfer switch or distribution-level STS is evaluated, if applicable.
- Does the load include a transformer or motor? If so, the transition strategy and inrush current should be considered separately.
In home and small office settings, most of these questions answer "one line, one UPS"; so no STS is required. For this type of use UPS for home and small office is a more appropriate starting point. In larger and more critical facilities, STS, UPS, battery and distribution should be considered as a system together.
For exploration, maintenance and technical service
Correct operation of STS; It depends on the fact that the resources are truly independent, the UPS and battery system is healthy and regular maintenance. Bempower provides sales, installation, periodic maintenance and technical service for all brands of UPS, battery packs and inverters; It can make on-site exploration in Istanbul and surrounding provinces. To evaluate the supply architecture, UPS and battery status in your facility or to create a periodic maintenance plan from the contact page You can contact us.
- IEC 62310-3:2008 Static transfer systems (STS) - Part 3: Method for specifying performance and test requirements — IECEE / IEC, 2008. https://www.iecee.org/certification/iec-standards/iec-62310-32008
- BS EN 62310 - Static transfer systems (STS) (multi-part standard sheet) — BSI Group, 2025. https://landingpage.bsigroup.com/LandingPage/Series?UPI=BS+EN+62310
- Voltage Thresholds for Distribution Planning (ITIC and CBEMA curves) — EPRI. https://restservice.epri.com/publicdownload/000000003002010996/0/Product
- Systems and methods for self-learning of transformer inrush characteristics to optimize transfer times in static transfer switch (US 11923724) — USPTO. https://image-ppubs.uspto.gov/dirsearch-public/print/downloadPdf/11923724
- Systems and methods of accelerating transfer in a static transfer switch (US 11682920) — USPTO. https://image-ppubs.uspto.gov/dirsearch-public/print/downloadPdf/11682920
- Static Transfer Switch: Ideal Solution Across a Spectrum of Applications — EC&M / Power Quality Magazine. https://www.ecmweb.com/power-quality-magazine-archive/article/20884791/static-transfer-switch-ideal-solution-across-a-spectrum-of-applications
Resources