When it is understood that it is time to replace the batteries, the job is not over; that's when the part that needs attention begins. An incorrectly selected battery, a single block connected upside down, or a loose terminal can cause the new battery group to not deliver the expected time at the first outage.
How to understand the time for change When to replace a UPS battery We explained it in our article. In this article, we describe the process that follows the decision step by step, from preliminary assessment to delivery of old batteries.
1. Preliminary Assessment
Before the replacement, the model of the UPS, the battery arrangement, the number of batteries in the string, the number of parallel strings and the type of batteries are determined on site. The voltage and internal resistance per battery are measured, the physical condition of the batteries and the environment in which they operate are checked.
At this stage Single battery or whole group The question is also answered. In a young array, a single battery that fails prematurely can be replaced with a suitable new one; in an aged array, the renewal of the whole group is evaluated. The decision is made according to the condition of the batteries and the manufacturer's instructions; justification Battery Array and Series-Parallel Connection We explained it in our article.
2. Choosing the Right Battery
The new battery is not selected because it fits into the casing of the old one. The following are considered together in the selection:
- System voltage and lineup: The battery voltage and quantity must be compatible with the DC bus voltage of the UPS.
- Capacity and backup time: The requested time is recalculated with the load; the loads may have changed since installation.
- Battery technology: VRLA (AGM or gel) batteries are mostly used in UPSs. Different technologies are not interchangeable because they only keep measurements.
- Dimensions and connection structure: Cabinet or rack layout, terminal type and cable connections.
- Charging System: The charging voltage of the UPS and the manufacturer's battery requirements.
The new battery does not have to be the same brand as the old one; it must be electrically and technically compatible.
3. Change Plan and Business Continuity
Whether the replacement can be made without turning off the UPS is predetermined by the structure and redundancy of the system:
| Structure of the system | Load during replacement |
|---|---|
| Hot-swappable battery modules | If the model allows, the module is replaced while the UPS is running; the load continues to be fed from the UPS. |
| Multiple parallel sequences | If each array has its own allocation element, one array is allocated and the others remain active; during this time, the backup time is shortened. |
| Single array | The behavior varies depending on the model: some UPSs continue to operate from the mains with an alarm, others do not operate without batteries. Even if it does, if the power goes out during this time, the load is not protected. |
| With maintenance bypass | The load is supplied directly from the mains; the protection of the UPS is disabled. |
The time the load is unprotected is kept as short as possible and scheduled for when the workload is lightest. What bypass passes mean What is UPS bypass You can find it in our article.
4. Safe Disassembly
A battery string carries a dangerous DC voltage even if the UPS is switched off and can deliver very high current in a short circuit. Dismantling is therefore carried out in a certain order:
- The battery string is separated from the UPS by a battery switch or fuse.
- The connection pattern is noted or photographed, the batteries are marked with a sequence number.
- The connections between the batteries are opened, disassembling the array; insulated tools are used, exposed terminals are sealed.
- Swollen or leaking batteries are handled separately; since batteries are heavy, lifting and carrying also require a plan.
5. Mounting: Polarity and Torque
New batteries are inserted, terminals and fasteners are checked. Assembly has two critical details:
- Polarity: In each connection, the positive and negative terminals are checked separately. A single battery connected in reverse reduces the total voltage of the array, which itself is damaged during charging.
- Torque: The connection screws are tightened with a torque wrench to the value specified by the battery manufacturer. A loose connection becomes hot; an overtightened terminal can be damaged.
Before the string is connected to the UPS, its total voltage is measured and compared to the expected value, then the terminal covers are installed. Checking the number of batteries and capacity settings in the UPS and arming the battery switch in the order in the manufacturer's instructions is done; in some models, these settings are entered while the device is running. Further checks and tests Commissioning after battery replacement We discussed it in our article.
6. Delivery of Old Batteries
Lead-acid batteries are hazardous waste; they are not thrown away, nor are they kept in a random corner. The terminals of the dismantled batteries are insulated against short circuits, transported vertically, and leaking batteries are also protected. Lithium batteries are collected and transported under their own conditions. Delivery and disposal are carried out in accordance with the relevant legislation.
Can You Do Battery Replacement Yourself?
In some small desktop UPSs, battery replacement is left to the user by the manufacturer; in these, only the steps described in the user manual are followed with the batteries that the manufacturer deems appropriate; if unsure, seek technical support. For systems connected to the panel, with an external battery cabinet or with multiple batteries, replacement, battery connections and settings Authorized Technical Personnel , with insulated tools and in accordance with the manufacturer's instructions. Do not interfere with the battery cabinets and terminals yourself.
Battery replacement at a glance
UPS battery replacement involves eight successive steps, from preliminary assessment to delivery of old batteries.
Most of the steps are done before or after installing new batteries. You can find the details of each step in the rest of the article.
Frequently Asked Questions
01Does the UPS have to shut off during battery replacement?
02How long does a battery replacement take?
03Do new batteries need to be the same brand as the old ones?
04Do new batteries come with a warranty?
05What happens to old batteries?
Let's Plan Your Battery Replacement
We replace the batteries of UPS of all brands and models throughout Istanbul and in the surrounding provinces. The process from preliminary evaluation to commissioning Battery Replacement and Reconditioning page. The make and model of your UPS, the number of batteries and the information on the battery labels Send us; Let's plan the change together.